Cabrini Hospital Chilled Water Infrastructure Upgrade

Strengthening cooling resilience and operational flexibility within a live healthcare environment.

Role of A.G. Coombs

A.G. Coombs was engaged to deliver a chilled water infrastructure upgrade at Cabrini Hospital in Malvern, converting the existing system into a true primary and secondary configuration servicing critical clinical buildings. While the overall design intent was established by the consultant, A.G. Coombs played a central role in adapting the design to suit the physical constraints of the site and developing a constructable solution capable of being delivered without disruption to hospital operations.

The works were completed in a fully operational hospital environment, requiring the chilled water network to remain live throughout construction. A.G. Coombs applied its specialist expertise across engineering, drafting, prefabrication, installation and commissioning to integrate the new infrastructure while maintaining uninterrupted service to operating theatres, ICU and adjacent clinical spaces.

Challenges

The project presented significant logistical and operational challenges due to its location within a live hospital and the constrained nature of the plant areas. Large mechanical equipment and pipework had to be transported through restricted access routes, including lifts with limited capacity and tight spatial tolerances. To manage these risks, project management, engineering and site teams undertook detailed site inspections to confirm access pathways, clearances and sequencing requirements before installation commenced.

Chilled water upgrades are typically undertaken during periods of reduced load; however, this project required delivery during higher demand conditions. Risk was mitigated through the installation of valved tee connections on the existing system, allowing new pipework to be connected in advance and enabling a staged transition to the new infrastructure. This approach minimised shutdown durations, reduced operational risk and allowed the existing system to remain available as a contingency during changeover.

Additional complexities included managing acoustic constraints within sensitive clinical environments, satisfying seismic requirements in an existing building not originally designed to current standards, coordinating multiple pipe freezes, and carefully planning noisy works to align with hospital operations. Close collaboration with specialist suppliers and subcontractors was essential to mitigate these risks while maintaining safety and program certainty.

Approach and Methodology

A.G. Coombs was involved early in the project, providing constructability advice and high-level methodology during the design development phase. This early engagement enabled practical input into system layout, staging and installation sequencing, ensuring solutions were efficient, buildable and aligned with Cabrini’s operational priorities.

As the project progressed into delivery, A.G. Coombs led a collaborative, multidisciplinary approach integrating engineering, drafting, prefabrication and site installation teams. Detailed construction programming, rigorous risk planning and proactive stakeholder coordination underpinned a disciplined execution strategy.

Prefabrication was utilised where possible to reduce on-site works and installation duration, while close coordination with controls and commissioning specialists ensured seamless integration of the new pumps, headers and control systems.

Key Outcomes

The upgraded chilled water system has provided Cabrini Hospital with improved system control, increased capacity for future expansion and enhanced energy efficiency. The new infrastructure supports both existing clinical demands and planned developments, delivering long-term operational resilience.

The project was delivered safely within a live hospital setting, maintaining uninterrupted cooling to critical care areas and reinforcing A.G. Coombs’ reputation for delivering complex healthcare infrastructure upgrades. The successful outcome has strengthened the client relationship and positioned A.G. Coombs as a trusted partner for future major infrastructure projects across the health sector.

Project Overview

Project Name: Cabrini Hospital Chilled Water Infrastructure Upgrade

Location: Melbourne VIC

Client: Cabrini Hospital

Year Completed: 2025

Project Type

Infrastructure Upgrade

Related Articles

December 16, 2025 in News

Co-Designing for Better Care

With an extensive pedigree in healthcare facilities, A.G. Coombs delivers building services solutions that prioritise wellbeing and recovery. For the ...

October 13, 2025 in Our Experience

101 Collins Street — Electrifying an Icon

101 Collins Street is a Melbourne landmark attracting some of Australia’s blue-chip corporations to occupy its prestigious location. In an age of gr...

Related Case Studies