Global Landmark – Martin Place

October 27, 2025

A new public transport-led integrated, retail and public precinct at Martin Place in Sydney incorporates an underground Metro station and two new commercial buildings in Sydney’s civic, cultural and financial centre.

Sydney Metro Martin Place is one of eight new stations built as part of the multi-billion-dollar reimagining of Sydney’s public transport network.

Delivered by Macquarie Group for the NSW Government, the project includes the construction of a new Metro station integrated with commercial, retail and public spaces.

Levelling up

As mechanical services contractor for the underground Metro station,
A.G. Coombs also delivered mechanical services to 1 Elizabeth, the 39-storey commercial office building at 1 Elizabeth Street, which was completed in
June 2024.

Located above the northern station entrance, the landmark JPW-designed building has a carefully-scaled alignment to the connecting heritage-listed
50 Martin Place building with large, stepping floorplates and a central open atrium providing natural light and ventilation.  The integration of the two buildings forms Macquarie Group’s new global headquarters.

A.G. Coombs’ role included the delivery of base building mechanical services for Macquarie Group across 27 levels.

The fitout features a high efficiency mechanical services design incorporating passive chilled beams with underfloor displacement primary air and heat recovery systems.

Electric dreams

All plant serving the building is electric requiring the rooftop plantroom to accommodate a prefabricated heating hot water (HHW) plant consisting of
14 electric heat pumps. Consideration was also given to maintenance and lifecycle, with the building maintenance unit (BMU) altered to cater for the installation and future replacement of plant.

The heat pump plant and associated controls are designed in series and provide significant flexibility through their reverse cycle capability. Consequently, both heating hot water and chilled water (CHW) can be generated concurrently.

Infrastructure for this plant, including pipes, pumps, risers, coils and heat exchangers was also redesigned to suit the limited heat pump temperatures (up to 55˚C) that are lower than traditional gas-fired plant (˜80˚C).

According to A.G. Coombs Senior Engineer Morgan Smith, the complexities associated with this change were overcome through careful, considered design that took into account the operating delta T (temperatures) of the heat pump system.

Image: JPW

Efficiency meets innovation

Incorporation of exposed overhead services in the fitout design demanded an eye for detail during construction and led A.G. Coombs to complete preassembly and testing of the passive chilled beam overhead valve units off-site.

“The opportunity for repetitive prefabrication was negated by the changing nature of each stepping floorplate, resulting in bespoke construction being carried out on each floor,” says Dean Allmark, A.G. Coombs Project Manager.

“The result is a high-end, industry-leading finish that reflects the world-class vision for the building.”

A.G. Coombs responded to an evolving project design for 1 Elizabeth with technical expertise and experience, and a commitment to close collaboration with our team and clients.

This article originally appeared in BE – Building Efficiency 2024 – 2025 magazine.

Loading ratings...

Latest News

December 17, 2025 in News

2025 in 25 Seconds

Season’s Greetings from everyone at the A.G. Coombs Group of Companies

December 16, 2025 in News

Co-Designing for Better Care

With an extensive pedigree in healthcare facilities, A.G. Coombs delivers building services solutions that prioritise wellbeing and recovery. For the ...